Completed Contracts

John Clayden Constructions have worked for numerous major construction companies, as listed below, and enjoy the reputation of getting repeat work from many of them due to outstanding performance and high quality of works.

  • Lend Lease
  • Leighton Constructions
  • John Holland
  • Thiess
  • Laing O’Rourke
  • Cockram
  • Abigroup
  • Hansen Yuncken

 

2022

JCC UGL Kangy Angy Works

Construction of transformer bund base slab and walls 6 metres in overall height. Including specialised civil/hydraulic works within JCC’s scope. JCC supplied all permanent materials for the project applicable to their scope of works.

2021

ATB Morton Tomago Works

JCC have been engaged by ATB Morton to carry out works within the Tomago Precinct. Initial works consisting of works to Energy Renaissance Lithium Project where JCC are carrying out concreting works to large surface areas for both building and civil areas. JCC have also been engaged to carry out various other concrete construction works through ATB Morton such as Advanciv Facility and SEW Project also requiring JCC’s sound ability to carry out works to large surface areas in accordance with requested project timeframes

2021

Acciona Belford to Golden Highway Culverts

3 x culvert structures constructed for Stormwater Management in accordance with RMS B80 Concrete Specification. JCC Supply/Testing/Placement of concrete in accordance with RMS B80 specification. Vertical and horizontal suspended formwork to culverts. JCC also responsible for grouting in of precast culvert crown bases and sealing of all precast culvert joints

2021

RTC SIMS Metal Gosford

Construction of 3500 m2 heavy duty hardstand areas to Sims Metals Facility and attached ancillary building structures. Supply of all permanent materials relevant to JCC’s works

2021

Charterpac Sheffeild Project

Detailed excavations, Construction of 1000 m2 suspended formwork to Level 01 Office and Warehouse areas. Construction of super flat floor areas to warehouse through use of laserscreed works- 4600 m2 total. 3500 m2 civil pavement areasSupply of all permanent materials relevant to JCC’s works including specialised jointing within warehouse.

2021

Richard Crookers Constructions Knights Centre of Excellence

Construction of 4000m2 building surface waffle pod slabs, Supply of all permanent materials related to JCC’s scope of works. Vertical and suspended formwork to Flood Refuge Structure within building

2020

Dungog Bioreactor

JCC have completed works at Dungog Waste Water Treatment plant. These works consisted of the main bioreactor structure along with several ancillary buildings required for the support infrastructure within the waste water treatment plant. The main bioreactor structure was poured in two separate with a 32m and 47m boom pumps being implemented to carry out the works. The total volume of Pour 1 was 140m3 and Pour 2 being 75m3.

Overall wall height was 5 metres and walls varying from 250mm to 400mm in overall thickness.

2020

Kurri Kurri Clarifier

Works at Kurri Kurri consisting of construction of new clarifier structure (circular formwork structure) and other smaller ancillary buildings.
Structural Consultants originally had the clarifier structure (water retaining) as a series of pours with pour breaks throughout. JCC personnel saw the opportunity to pour the entire structure in one monolithic pour in order to achieve one uniform clarifier wall structure. The total volume within the wall pour was 75m3 of quality concrete.

Overall height of tank structure was 4.8 metres in height along with a circumference of 52 lineal metres

2019

New Intercity Fleet Train Maintenance Facility, John Holland

2015-2019

Williamtown Air Base Redevelopment, Lend Lease – Various Concrete & Formwork Packages

2018

Cessnock Correctional Facility, 330 bed expansion project – Richard Crookes Constructions

2015

Hexham Train Support Facility- Leightons Contractors

  • 8,186m2 Concrete Surface Area
  • 4,265m3 Concrete Placed
  • 561 Tonne Reinforcement
  • 2,112m2 Steel Mesh

2013

Tamworth Hospital, Tamworth, Richard Crookes / Abi Group JV

  • 34,500m2 Concrete Surface Area
  • 11,200m3 Concrete Placed
  • 750 Tonne Reinforcement
  • 14,300m2 Steel Mesh

2013

Masters, West Gosford

  • 21,800m2 Concrete Surface Area (Slab Finish to High Specification Requirements)
  • 4,200m3 Concrete Placed
  • 70 Tonne Reinforcement
  • 19,000m2 Steel Mesh

2013

Student Accommodation – Newcastle University – John Holland

  • 23,400m2 Concrete Surface Area
  • 9,800m3 Concrete Placed

2012

Westrac Facility, Tomago, Abigroup

  • 66,800m2 Concrete Surface Area
  • 34,000m3 Concrete Placed
  • 795 Tonne Reinforcement
  • 35100m2 Steel Mesh
  • 25,000m of Jointing Systems

2012

Research Facility, John Hunter Hospital Newcastle, Cockram

2011

Greta Locomotive Facility, Greta, Abigroup

  • 11,200m2 Concrete Surface Area
  • 4,300m3 Concrete Placed

2008

Energy Australia Stadium, Newcastle, John Holland

  • 23,100m2 Concrete Surface Area
  • 13,300m3 Concrete Placed
  • 1,850 Tonne Reinforcement
  • 800m2 Steel Mesh

2007

Mater Hospital, Newcastle, AbiGroup

  • 12,000m3 Concrete Placed
  • 3,000 Tonne Reinforcement

2007

Liddell Mine, Workshop Extensions, Hansen Yuncken

  • 2,100m2 Concrete Surface Area
  • 1,946m3 Concrete Placed
  • 81 Tonne Reinforcement

2004

Woolworths Distribution Centre, Warnervale, John Holland

  • 90,000m2 of building slabs and external pavements
  • 16,400m of Jointing Systems

Contact us with any enquiries